Before testing, relay technical
data and set voltage value to be checked.
. Relay connection to be checked according to
approved technical design. Particular attention should be
paid to the correct wiring and value of any external resistors indicated
on the wiring diagram/relay rating information.
. With the relay removed its case, check
electrically that the CT shorting switch is closed.
. Relay operating voltage to be tested by injection
voltage by test plug. Increase
the voltage until the relay just operates. Noted operating voltage which should correspond to the
setting VR
of the relay with a tolerance of ± 10%. Note the current in the relay, it should be
approximately 38mA at setting. Note Drop
off/Pick-up ratio, should be greater than 50%.
. Stability
test of the relay to be performed by secondary current injection.
. Stability test to be performed for two
cases: in protected zone and out of protected zone.
. Operation of the relay trip contacts and
indicators to be checked